SUBPART 217.74--UNDEFINITIZED CONTRACT ACTIONS
(Revised December 09, 1998)

217.7400 Scope.
This subpart prescribes policies and procedures implementing 10 U.S.C. 2326.

217.7401 Definitions.
As used in this subpart-

217.7402 Exceptions.
The following undefinitized contract actions (UCAs) are not subject to this subpart, but the contracting officer should apply the policy to them (and to changes under the Changes clause) to the maximum extent practicable- 217.7403 Policy.
DoD policy is that undefinitized contract actions shall- 217.7404 Limitations.

217.7404-1 Authorization.
The contracting officer shall obtain approval from the head of the contracting activity before-

217.7404-2 Price ceiling.
UCAs shall include a not-to-exceed price.

217.7404-3 Definitization schedule.

217.7404-4 Limitations on obligations.
The Government shall not obligate more than 50 percent of the not-to-exceed price before definitization. However, if a contractor submits a qualifying proposal before 50 percent of the not-to-exceed price has been obligated by the Government, then the limitation on obligations before definitization may be increased to no more than 75 percent (see 232.102-70 for coverage on provisional delivery payments).

217.7404-5 Exceptions.

217.7404-6 Allowable profit.
When the final price of a UCA is negotiated after a substantial portion of the required performance has been completed, the head of the agency shall ensure the profit allowed reflects- 217.7405 Definitizations.
For each definitization modification, the contracting officer shall include all data required by 243.171.

217.7406 Contract clauses.