Q. What is Earned Value Management?
A. Earned Value Management, or EVM, is a widely accepted industry best practice
for project management that is being used across the Department of Defense
(DoD), the Federal government, and the commercial sector. It is the use of an integrated management
system that coordinates the work scope, schedule, and cost goals of a program
or contract, and objectively measures progress toward these goals. EVM is a tool used by program managers to: (1) quantify and measure program/contract
performance, (2) provide an early warning system for deviation from a baseline,
(3) mitigate risks associated with cost and schedule overruns, and (4) provide
a means to forecast final cost and schedule outcomes. To see a simple example of how EVM actually
works, click on this illustrative explanation.
Q. What are the EVM System guidelines?
A. The implementation and use of EVM is governed by an industry
standard—ANSI/EIA-748, Earned Value
Management Systems. ANSI/EIA stands
for American National Standards Institute/Electronic Industries Alliance. The standard establishes 32 minimum
management control guidelines
for an Earned Value Management System (EVMS) to ensure the validity of the
information used by management. DoD and
the Federal government at large have adopted the guidelines in ANSI/EIA-748 for
use on government programs and contracts.
The DoD EVM policy requires contractor management systems compliant with
the current version of ANSI/EIA-748 whenever EVM is required. In DoD, the Defense Contract Management
Agency (DCMA) is the executive agency for EVMS and in this capacity has
responsibility for determining that contractor systems comply with
ANSI/EIA-748.
Q. There appears to be a lot of “jargon”
associated with EVM. What do all the
terms and acronyms mean?
A. The Glossary of EVM Terms
and the "Gold
Card" are good references for more information on EVM terms and
acronyms.
Q. The new EVMS Defense Federal Acquisition
Regulation Supplement (DFARS) clauses were published in April 2008. What is the effective date for their use on
DoD contracts?
A. The final
rule on the new EVMS DFARS clauses was published in the Federal Register on April 23, 2008. The new clauses (252.234-7001 for
solicitations and 252.234-7002 for contracts) shall be applied to newly awarded
DoD contracts effective immediately.
Existing contracts that contain the previous clauses (252.242-7001 and
252.242-7002) do not require modification to apply the new clauses.
Q. Should the EVMS clauses in the
FAR be put on DoD contracts?
A. No, the FAR clauses should not be put on DoD contracts. The FAR allows for Federal departments and
agencies to use clauses that are “substantially the same” as the FAR clauses. The EVMS DFARS clauses are substantially the
same and therefore satisfy the FAR requirements. In fact, Section 234.203 of the April 2008
DFARS specifically states that the DFARS will be used instead of the FAR. It should be noted, however, that the FAR
contains a clause for pre-award IBRs but the DFARS do not. Therefore, if a program manager elects to
conduct a pre-award IBR on a DoD contract, he or she should include that
requirement in the statement of work.
Q. I understand that the DoD EVM policy
was revised in March of 2005. What were
the major changes?
A. On March 7, 2005, the Defense Acquisition Executive signed a memorandum approving some relatively
significant changes to the Department’s longstanding EVM policy. The policy was revised to provide consistency
in EVM application and implementation across DoD programs and to better manage
the programs through improvements in DoD and industry EVM practices. The revised policy requires that all EVM
applications comply with ANSI/EIA-748.
It also mandates new EVM application thresholds, which are now in
then-year dollars. Other key changes
include: improving and renaming the
Contract Performance Report (CPR) (previously called the Cost Performance
Report); expanding the use of the Integrated Master Schedule (IMS); clarifying
the requirement for Integrated Baseline Reviews (IBRs); and eliminating the
Cost/Schedule Status Report (C/SSR).
Q. The DoD EVM application
thresholds are now in then-year dollars rather than base-year dollars. What’s the difference and why was this change
made?
A. Then-year dollars are current dollars that reflect the impact of inflation
over time, such as the dollars in your wallet.
Base-year dollars are constant dollars that reflect the cost of the
program as if inflation had not occurred (the cost to acquire a multi-year
system if you paid for it in advance in one specific year). The EVM application thresholds were changed from
base-year dollars to then-year dollars because then-year dollars represent a
more accurate measure of the value of contracts. Contracts are awarded in then-year dollars,
which represent what the government has to pay.
Base-year dollars are used primarily for cost estimating purposes and
are not good indicators of current contract value. The threshold dollar values will be
reassessed periodically and revised as necessary to keep pace with future
inflation.
Q. Are the changes to the DoD EVM
policy retroactive to existing contracts?
A. No, the changes to the EVM policy are not retroactive to existing
contracts. However, they are effective
immediately on new cost or incentive contracts awarded in response to solicitations
or requests for proposals issued on or after April 6, 2005 (30 days from the date
of the memorandum signed by the Defense Acquisition Executive). While the changes are not retroactive, program
managers are not precluded from imposing new or different EVM requirements on
existing contracts if the benefits outweigh the costs. Remaining contract duration and estimated
costs, as well as other risk factors, should be taken into consideration when
determining whether to modify the EVM requirements on existing contracts. In addition, the costs associated with the
modifications will be borne by the government.
Q. What is the policy on the
retroactivity of the requirement for EVMS validations for contractors
performing work for DoD?
A. To reiterate, the changes to the EVM policy are not retroactive to existing
contracts (see the answer to the previous question). This includes EVMS validations that were not
required under the old policy but would be under the new policy. However, if a contractor (or subcontractor)
without an EVMS validation is awarded a new cost or incentive contract that is
valued at or greater than $50 million, validation is then required.
Q. What impact do the new
application thresholds have on determining when the use of EVM is required on
DoD contracts?
A. The old DoD policy required EVM on development contracts over $73 million
and procurement and operations and maintenance contracts over $315
million. It also required C/SSRs on
contracts over $6.3 million. The March
2005 revisions to the policy raised the lower threshold from $6.3 million to
$20 million and lowered the upper threshold from $73 million and $315 million
to $50 million (it also eliminated the separate thresholds for development and
procurement). Under the new DoD policy, EVM
compliance is required on cost or incentive contracts, subcontracts, intra-government
work agreements, and other agreements valued at or greater than $20
million. An EVMS that has been formally
validated by DCMA and accepted by the cognizant contracting officer is required
on cost or incentive contracts, subcontracts, intra-government work agreements,
and other agreements valued at or greater than $50 million.
Q. Won’t the changes to the
application thresholds increase the quantity of DoD contracts that require the
use of EVM?
A. While on the surface it appears as though this would be true, it is in fact
not the case. A comprehensive business
case analysis conducted in November 2004, based on DoD contracts data supplied
by DCMA and industry-representative contracts data provided by the National
Defense Industrial Association, concluded that the new application thresholds would
result in significant cost avoidance relative to the former thresholds. Specifically, the cost of eliminating C/SSRs
on low dollar value contracts (those valued below $20 million) more than
offsets the increased cost of additional CPRs and tailored CPRs, which replace
C/SSRs, on the higher dollar value contracts (those valued at $20 million and
above).
Q. When deciding whether a DoD contract
requires the use of EVM, how do I determine the contract value against which to
apply the application thresholds?
A. When determining the contract value for the
purpose of applying the EVM thresholds, the total contract value in then-year
dollars, including planned options (CLINS) placed on contract at the time of
award, should be used.
Q. Does the DoD EVM policy apply to
programs or contracts that are not governed by the acquisition policy in the
DoD 5000 series documents?
A. All “major acquisitions” with development effort, regardless of whether they
have been designated as DoD acquisition programs, are subject to the EVM policy
in accordance with the direction in Office of Management and Budget (OMB)
Circular A-11, Part 7, and the corresponding Capital Programming Guide.
Q. If I have an existing contract
valued at less than $20 million and intend to sign a contract modification that
will increase the total value of the contract over the $20 million EVM
application threshold, am I required to modify the contract to place the new
EVM requirements on the contract?
A. Generally speaking, the changes to the EVM policy are not retroactive to contracts
awarded in response to solicitations or requests for proposals issued before
April 6, 2005. However, the program
manager is strongly encouraged to add or change the EVM requirements when
modifying an existing contract to proceed to a subsequent acquisition phase, or
in cases where the duration of the contract exceeds 12 months, the value of the
contract reaches $50 million or greater, and/or the nature of the work imposes
risk to the government. The costs
associated with the modifications will be borne by the government. To minimize the likelihood of this situation
occurring, the program manager should impose an EVM requirement on the contract
when it is initially awarded if there is knowledge at the time that the value
of the contract will grow to reach or exceed $20 million.
Q. What types of contracts does the
DoD EVM policy apply to? Does it apply
to fixed price incentive contracts?
A. The EVM policy applies to all cost or incentive type contracts,
subcontracts, intra-government work agreements, and other agreements valued at
or greater than $20 million. Since a
fixed price “incentive” contract is by definition an incentive contract, it
requires the implementation of EVM if it is valued at or greater than $20
million.
Q. Has the DoD policy
on applying EVM to Firm-Fixed Price (FFP) contracts changed?
A. When
the EVM policy was revised in March 2005, the Defense Acquisition Executive decided
to retain the existing policy for FFP contracts based on the rationale
that, if the risk warrants the need for EVM to manage, FFP may not be the
appropriate contract type. Therefore, the use of EVM on FFP contracts continues to be limited to cases where the
program manager believes there is significant schedule risk and/or concern
about the impact of cost pressures on product or service quality. In these cases, the program manager should
ask for a waiver from the program decision authority to implement EVM on
individual FFP contracts. In
addition, if a FFP contract is used for development or integration efforts
valued at or greater than $20 million, the program manager is required by OMB
(see next question) to use EVM and should request a waiver to do so. Such waiver requests must include a business
case analysis that provides the rationale for why a cost or incentive contract
was not an appropriate contracting vehicle.
Q. Isn’t DoD’s policy
on applying EVM to FFP contracts in conflict with OMB’s direction?
A. No, the DoD EVM policy only appears to differ from the OMB policy. If the
DoD policies on selecting contract type and applying EVM are followed, the
instances of noncompliance with the OMB policy will be the exception not the
rule. While the OMB policy does not exempt FFP contracts from the EVM
requirements, OMB's focus is on development efforts in both the planning and
acquisition phases. DoD does not as a matter of course use FFP contracts for
development and integration efforts, which are inherently more risky to the
government. (OMB also discourages the use of FFP contracts for
development efforts.) Therefore, in DoD the use of FFP contracts is
typically limited to mature, lower risk production work, which uses
means other than earned value to manage contract performance. Higher risk
development work is usually accomplished with cost type contracts,
which require EVM. Low rate initial production and early
production contracts tend to be of the fixed price incentive type, which
also require EVM. In order to preclude
any disconnects with regard to the applicability of EVM based on contract type,
DoD program managers need to adhere to the Department's policies on selecting
contract type and applying EVM. And, when
a FFP contract is chosen for development work, the program manager needs to apply
EVM to the contract and should request a waiver from the program decision
authority to do so.
Q. How should I handle a situation where a contractor
proposes to use its EVMS to manage a DoD contract to which EVM is not being
applied, e.g, a FFP contract?
A. The contractor should not be prohibited from
employing its EVMS if the use of EVM is an ingrained corporate process. DoD, however, would not typically require EVM
reporting (Contract Performance Report and Integrated Master Schedule) on contracts
to which EVM is not being applied, such as FFP contracts. When the contractor’s EVMS is an ingrained
corporate process and no reporting to DoD is required, DoD should incur little
or no implementation costs associated with use of the contractor’s EVMS. But, in cases where there may be some minor
costs, they should be negotiated up front with the contractor.
Q. How do I apply the DoD EVM policy
to contracts for which the nature of the work is level of effort?
A. As a
general rule, EVM is required on cost or incentive contracts valued at or
greater than $20 million; however, it may be necessary to consider the nature
of the work associated with the contract when determining EVM applicability. In the EVM context, there are two basic
classifications of the nature of work—discrete and level of effort (LOE). Discrete work is related to the completion of
specific end products or services and can be directly planned, scheduled, and
measured. LOE is effort of a general or supportive nature that does not produce
definite end products (time and materials and services contracts may contain
LOE work). The application of EVM on
work that is LOE in nature may be impractical and inefficient. Therefore, if the work on a contract is
exclusively LOE, it may be appropriate to request a waiver to the EVM policy
from the program decision authority. When
possible, waiver requests should be included in the program acquisition
strategy. If EVM is waived for a
contract due to the nature of the work, the program manager is required to
implement an alternative method of management control to provide advanced
warning of potential performance problems.
Waivers to the EVM policy should
be the exception not the rule because they are appropriate only in cases where
a cost or incentive contract is being used for work that is exclusively
LOE. See the DoD Earned
Value Management Implementation Guide for additional guidance on applying
EVM on LOE work.
Q. How do I get a waiver to the
DoD EVM policy?
A. Waivers to the EVM policy—just like any other policy waiver—should be
obtained on a case-by-case basis from the appropriate program decision
authority using the pre-existing processes.
However, requests to waive specific EVM requirements can also be
requested via inclusion in the acquisition strategy that is approved by the
program decision authority.
Q. On Indefinite Delivery/Indefinite
Quantity (ID/IQ) or task order types of contracts, how should the application
of EVM be determined—based on the total contract value or the individual task
orders?
A. For ID/IQ or task order types of contracts, the application
of EVM based on dollar threshold is assessed at the computed total contract
value and not by each separate order. To
determine EVM applicability, anticipated cost or incentive orders should be
summed to reach the computed total contract value. FFP orders are generally not included in that
summation, unless the work involves development or integration effort. See
the DoD
Earned Value Management Implementation Guide for additional guidance on
applying EVM to ID/IQ or task order types of contracts.
Q. How do I apply EVM on a contract
that includes FFP CLINS, as well as cost and/or incentive CLINS?
A. If a contract type is mixed, the EVM policy should be applied separately to
the different parts (contract types). In
other words, the use of EVM on any cost or incentive parts that are valued at
$20 million or greater would be required but EVM would not be required on any
FFP parts, unless the work involves development or integration effort. See the DoD Earned
Value Management Implementation Guide for additional guidance on applying
EVM to mixed type contracts.
Q. Do the DoD EVM requirements flow
down to subcontractors?
A. Yes, the EVM requirements flow down to the subcontractor if the subcontract
is valued at or greater than $20 million. Subcontractors with contracts valued at or
greater than $50 million are subject to the EVMS validation requirement. In accordance with the DFARS clauses, the
prime contractor identifies the major subcontractors in its proposal. The government then determines, and specifies
by name in the prime contract, which of those major subcontracts must comply
with the EVM requirements.
Q. Does the DoD EVM policy require
pre-award IBRs?
A. No, the EVM policy does not mandate pre-award IBRs. The policy requires that IBRs be initiated as
early as practicable and that the timing of the IBRs take into consideration
the contract period of performance. The
IBR process should be conducted not later than 180 calendar days (6 months)
after: (1) contract award, (2) the
exercise of significant contract options, and (3) the incorporation of major
modifications. However, the policy does
not prohibit the use of pre-award IBRs in situations where they may be appropriate
and beneficial. If a program manager
elects to conduct a pre-award IBR on a DoD contract, he or she should include
that requirement in the statement of work.
Q. If I place funds transferred from
a DoD organization on a non-DoD contract, does the DoD EVM policy apply?
A. No, the contract will be awarded in accordance with the rules of the
organization receiving the transferred funds, and in accordance with the FAR as
applicable.
Q. Does the DoD EVM policy apply to
foreign suppliers?
A. Yes, the EVM thresholds and requirements apply to both domestic and foreign
contractors and subcontractors. In fact,
many foreign suppliers operate in countries that have EVM policies very similar
to those of the
Q. Where can I find the Contract
Performance Report (CPR) Data Item Description (DID), the forms for CPR Formats
1-5, and the Integrated Master Schedule (IMS) DID?
A. The approved CPR and IMS DIDs are available on the ASSIST web site. The CPR forms (Formats 1-5) are located on the
DoD Forms
Program web site in .pdf format. A
Microsoft Excel version of Formats 1-5 is available on both the OSD EVM web
site and the EVM
Community of Practice site on the AT&L Acquisition Community Connection
knowledge sharing system.
Q. What are the rules with regard
to reporting to the EVM Central Repository (CR)?
A. The EVM information (CPR, IMS, and CFSR)
for all ACAT I programs is required to be submitted directly to the EVM CR by
the reporting contractor. The EVM CR
should be the sole addressee on the contract data requirements lists (CDRLs)
for these reports. The use of a standard
electronic data exchange format is required for all reports. All data must be in a readable digital format
(e.g., pdf files are not acceptable). The
Extensible Markup Language standard (Project Schedule Cost Performance
Management message) is the preferred format. The American National Standards Institute X12
standard (839 transaction set) is also acceptable. On-line access to the data may be provided to
augment formal submission. See the EVM CR Manual for
additional guidance on the CR requirements.
Q. On CPR Format 1, Section 8 (f)
Management Reserve, column (15) is shaded. Does this mean that I cannot put management reserve
in this cell?
A. Management reserve data should be included in Section 6 (a), (b), and (c)
Estimated Cost at Completion under the Management Estimate at Completion
(1). As per the DID, the estimate at
completion in column (15) would only be for work included in the Performance
Measurement Baseline (PMB). Any impacts
due to additional risk, management reserve, or higher level management
knowledge would be included in Section 6 (1).
Q. On CPR Format 3, Section 6
Performance Data (b) Baseline Changes Authorized During Report Period, column
(2) through (15) are shaded. Does this mean
that I cannot put data in these cells?
A. That is correct. Data cannot be input
into shaded cells. Baseline changes should
be included in Section 6 (b) Baseline Changes Authorized During Report Period,
column (16) as a total value for each significant change. Differences between the beginning PMB time
phasing and the ending PMB time phasing in Format 3 should be amplified and
explained in Format 5.
Q. If a contract is rebaselined using
an Over Target Baseline (OTB) or a single point adjustment, does that change
the EVM requirements for the contract?
A. The changes to the EVM policy are not retroactive to contracts awarded in
response to solicitations or requests for proposals issued before April 6,
2005. However, the policy does not
prohibit contract modifications to impose new or different EVM requirements
provided that the cost associated with the change is borne by the
government. The program manager should
consider the new contract value, the remaining contract duration, the risk
associated with the contract, and the cost/benefit tradeoff in determining how
to apply the EVM requirements to a rebaselined contract.
Q. The DoD EVM policy addresses the
IMS but does not address the Integrated Master Plan (IMP). Does this mean the IMP is not required?
A. The requirement for an IMP has not changed. Both the IMP and the IMS continue to be
important tools that provide significant assistance in the planning and
scheduling of work efforts. The IMP is a
contractual event-based plan consisting of a hierarchy of program events, with
each event being supported by specific accomplishments and completion criteria. The IMS is a time-based schedule that flows
directly from the IMP and provides the level of detail necessary for day-to-day
program/contract execution. The IMS is
typically requested through a CDRL. The
policy changes in March 2005 strengthened the requirement for an IMS DoD-wide
by requiring an IMS whenever a CPR is required. The aim of this change is to better integrate
cost and schedule reporting and to improve schedule performance.
Q. If the requirement for an IMS is
implemented on a contract option, must the existing contract be modified to
require an IMS?
A. The changes to the EVM policy are not
retroactive to contracts awarded in response to solicitations or requests for
proposals issued before April 6, 2005. However,
the decision to impose the IMS requirement on the original contract should be
made based on negotiations between the government and contractor, and should be
based on all relevant factors to include the dollar value and duration of the
contract, the degree of risk, and the nature of the work. If a decision is made to modify the contract,
keep in mind that the IMS can be tailored as appropriate within the bounds of
the policy. Detailed guidance on
tailoring the IMS can be found in the DoD Earned
Value Management Implementation Guide.
Q. Is there a DoD requirement for
a resource-loaded schedule?
A. No, the IMS DID does not prescribe a resource-loaded schedule, nor does it
prohibit resource loading in those situations where it is appropriate and
beneficial to do so.
Q. Who determines how the CPR and the
IMS will be tailored?
A. The program manager is ultimately responsible for determining how EVM
reporting will be tailored, but the degree of tailoring must be appropriate and
allowable within the bounds of the EVM policy. Both the CPR and the IMS are tailorable for
contracts valued at less than $50 million.
For example, reporting frequency, submission dates, and level of detail
can be negotiated. All relevant risk
factors should be considered when determining the degree of tailoring that is
appropriate. Detailed guidance on
tailoring the CPR and the IMS resides in the DoD Earned
Value Management Implementation Guide.
Q. How can the CPR and the IMS be
integrated if the information is maintained in different software applications?
A. The policy aims to link the CPR and the IMS by requiring the submission of
both reports any time EVM is required and mandating that a common work breakdown
structure that follows MIL-HDBK-881A
(Work Breakdown Structure Handbook) be used for both reports. The policy does not prescribe specific
software applications.
Q. Where can I find out more about EVM
and its uses in the DoD environment?
A. The DAU EVM Training
Center site contains training modules to familiarize users with the EVM
process and its application to DoD programs/contracts. The EVM Community of
Practice site also provides users with a variety of resources applicable to
EVM including tools, published articles, training material, a research library,
and an EVM discussion forum.
Q. Where can I find information on EVM
for industry users?
A. The National Defense Industrial Association’s Program Management Systems
Committee is the recognized body for subject matter expertise on ANSI/EIA-748. The Committee’s web site hosts several guides
that represent best practices in EVM application and implementation. The guides can be accessed from the EVM
Community of Practice site (click on “OMB Recommended References”). In addition, the Project Management Institute, College of
Performance Management (PMI/CPM) web site provides a forum for sharing
information in the private sector regarding EVM and its application in the
business environment. This site posts
conferences, training opportunities, and events of interest to all users of
EVM.