[Federal Register: May 22, 2000 (Volume 65, Number 99)]
[Proposed Rules]
[Page 32066-32069]
From the Federal Register Online via GPO Access [wais.access.gpo.gov]
[DOCID:fr22my00-31]
-----------------------------------------------------------------------
DEPARTMENT OF DEFENSE
48 CFR Part 215
[DFARS Case 2000-D300]
Defense Federal Acquisition Regulation Supplement; Profit
incentives To Produce Innovative New Technologies
AGENCY: Department of Defense (DoD).
ACTION: Proposed rule with request for comments.
-----------------------------------------------------------------------
SUMMARY: The Acting Director of Defense Procurement is proposing to
amend the Defense Federal Acquisition Regulation Supplement (DFARS) to
implement Section 813 of the National Defense Authorization Act for
Fiscal Year 2000. Section 813 requires DoD to review its profit
guidelines to consider whether appropriate modifications, such as
placing increased emphasis on technical risk as a factor for
determining appropriate profit margins, would provide an increased
profit incentive for contractors to develop and produce complex and
innovative new technologies.
[[Page 32067]]
DATES: Comments on the proposed rule should be submitted in writing to
the address shown below on or before July 21, 2000, to be considered in
the formation of the final rule.
ADDRESSES: Interested parties should submit written comments on the
proposed rule to: Defense Acquisition Regulations Council, Attn: Ms.
Amy Williams, PDUSD(AT&L) DP(DAR), IMD 3D139, 3062 Defense Pentagon,
Washington, DC 20301-3062. Telefax (703) 602-0350.
E-mail comments submitted via the Internet should be addressed to:
dfars@acq.osd.mil
Please cite DFARS Case 2000-D300 in all correspondence related to
this proposed rule. E-mail correspondence should cite DFARS Case 2000-
D300 in the subject line.
FOR FURTHER INFORMATION CONTACT: Ms. Amy Williams, (703) 602-0288.
SUPPLEMENTARY INFORMATION:
A. Background
This rule proposes amendments to the profit policy in DFARS Subpart
215.4 to implement Section 813 of the National Defense Authorization
Act for Fiscal Year 2000 (Public Law 106-65). DoD published an advance
notice of proposed rulemaking on February 10, 2000 (65 FR 6574), posted
a preliminary draft on potential changes on the Defense Procurement
Internet web site, and held a public meeting on February 23, 2000.
Representatives from Government and industry participated in the public
meeting.
The proposed rule amends the weighted guidelines method of profit
computation at DFARS 215.404-71 to combine the management and cost
control elements of the performance risk factor; to establish a new
``technology incentive'' range for technical risk; and, based on
comments received at the public meeting, to slightly modify some of the
cost control standards. In addition, the rule amends DFARS 215.404-4(b)
to clarify that DoD departments and agencies must use a structured
approach for developing a prenegotiation profit or fee objective on any
negotiated contract action when cost or pricing data is obtained.
This rule was not subject to Office of Management and Budget review
under Executive Order 12866, dated September 30, 1993.
B. Regulatory Flexibility Act
The proposed rule is not expected to have a significant economic
impact on a substantial number of small entities within the meaning of
the Regulatory Flexibility Act, 5 U.S.C. 601, et seq., because most
contracts awarded to small entities are below $500,000, are based on
adequate price competition, or are for commercial items, and do not
require submission of cost or pricing data. Therefore, an initial
regulatory flexibility analysis has not been performed. Comments are
invited from small businesses and other interested parties. Comments
from small entities concerning the affected DFARS subpart also will be
considered in accordance with 5 U.S.C. 610. Such comments should be
submitted separately and should cite DFARS Case 2000-D300.
C. Paperwork Reduction Act
The Paperwork Reduction Act does not apply because the rule does
not impose any information collection requirements that require the
approval of the Office of Management and Budget under 44 U.S.C. 3501,
et seq.
List of Subjects in 48 CFR Part 215
Government procurement.
Michele P. Peterson,
Executive Editor, Defense Acquisition Regulations Council.
Therefore, 48 CFR part 215 is proposed to be amended as follows:
1. The authority citation for 48 CFR part 215 continues to read as
follows:
Authority: 41 U.S.C. 421 and 48 CFR Chapter 1.
PART 215--CONTRACTING BY NEGOTIATION
2. Section 215.404-4 is amended by revising paragraph (b)(1)
introductory text to read as follows:
215.404-4 Profit.
(b) * * * (1) Departments and agencies must use a structured
approach for developing a prenegotiation profit or fee objective on any
negotiated contract action when cost or pricing data is obtained,
except for cost-plus-award-fee contracts (see 215.404-74) or contracts
with Federally Funded Research and Development Centers (FFRDCs) (see
215.404-75). There are three structured approaches--
* * * * *
3. Section 215.404-71-2 is revised to read as follows:
215.404-71-2 Performance risk.
(a) Description. This profit factor addresses the contractor's
degree of risk in fulfilling the contract requirements. The factor
consists of two parts:
(1) Technical--the technical uncertainties of performance.
(2) Management/cost control--the degree of management effort
necessary--
(i) To ensure that contract requirements are met; and
(ii) To reduce and control costs.
(b) Determination. The following extract from the DD Form 1547 is
annotated to describe the process.
----------------------------------------------------------------------------------------------------------------
Contractor risk Assigned Profit
Item factors weighting Assigned value Base (item 18) objective
----------------------------------------------------------------------------------------------------------------
21............. Technical............. (1) (2) N/A N/A
22............. Management/Cost (1) (2) N/A N/A
Control.
23............. Reserved.............. ................. ................ ................ ................
24............. Performance Risk N/A (3) (4)( 5)
(Composite).
----------------------------------------------------------------------------------------------------------------
1 Assign a weight (percentage) to each element
according to its input to the total performance risk. The total of
the two weights equals 100 percent.
2 Select a value for each element from the list in
paragraph (c) of this subsection using the evaluation criteria in
paragraphs (d) and (e) of this subsection.
3 Compute the composite as shown in the following
example:
----------------------------------------------------------------------------------------------------------------
Assigned
weighting Assigned value Weighted value
(percent) (percent) (percent)
----------------------------------------------------------------------------------------------------------------
Technical................................................... 60 5.0 3.0
Management/Cost Control..................................... 40 4.0 1.6
[[Page 32068]]
Composite Value............................................. 100 .............. 4.6
----------------------------------------------------------------------------------------------------------------
4 Insert the amount from Block 18 of the DD Form
1547. Block 18 is total contract costs, excluding general and
administrative expenses, contractor independent research and
development and bid and proposal expenses, and facilities capital
cost of money.
5 Multiply (3) by (4).
(c) Values: Normal and designated ranges.
------------------------------------------------------------------------
Normal value (percnet) Designated
range
----------------------------------------------------(percent)j-
Standard.......................................... 4 2 to 6
Alternate......................................... 6 4 to 8
Technology Incentive.............................. 8 6 to 10
------------------------------------------------------------------------
(1) Standard. The standard designated range should apply to most
contracts.
(2) Alternate. Contracting officers may use the alternate
designated range for research and development and service contractors
when these contractors require relatively low capital investment in
buildings and equipment when compared to the defense industry overall.
If the alternate designated range is used, do not give any profit for
facilities capital employed (see 215.404-71-4(c)(3)).
(3) Technology incentive. For the technical factor only,
contracting officers may use the technology incentive range for
acquisitions that include development or production of innovative new
technologies.
(d) Evaluation criteria for technical. (1) Review the contract
requirements and focus on the critical performance elements in the
statement of work or specifications. Factors to consider include--
(i) Technology being applied or developed by the contractor;
(ii) Technical complexity;
(iii) Program maturity;
(iv) Performance specifications and tolerances;
(v) Delivery schedule; and
(vi) Extent of a warranty or guarantee.
(2) Above normal conditions. (i) The contracting officer may assign
a higher than normal value in those cases where there is a substantial
technical risk. Indicators are--
(A) Items are being manufactured using specifications with
stringent tolerance limits;
(B) The efforts require highly skilled personnel or require the use
of state-of-the-art machinery;
(C) The services and analytical efforts are extremely important to
the Government and must be performed to exacting standards;
(D) The contractor's independent development and investment has
reduced the Government's risk or cost;
(E) The contractor has accepted an accelerated delivery schedule to
meet DoD requirements; or
(F) The contractor has assumed additional risk through warranty
provisions.
(ii) Extremely complex, vital efforts to overcome difficult
technical obstacles that require personnel with exceptional abilities,
experience, and professional credentials may justify a value
significantly above normal.
(iii) The following may justify a maximum value--
(A) Development or initial production of a new item, particularly
if performance or quality specifications are tight; or
(B) A high degree of development or production concurrency.
(3) Below normal conditions. (i) The contracting officer may assign
a lower than normal value in those cases where the technical risk is
low.
Indicators are--
(A) Acquisition is for off-the-shelf items;
(B) Requirements are relatively simple;
(C) Technology is not complex;
(D) Efforts do not require highly skilled personnel;
(E) Efforts are routine;
(F) Programs are mature; or
(G) Acquisition is a follow-on effort or a repetitive type
acquisition.
(ii) The contracting officer may assign a value significantly below
normal for--
(A) Routine services;
(B) Production of simple items;
(C) Rote entry or routine integration of Government-furnished
information; or
(D) Simple operations with Government-furnished property.
(4) Technology incentive range.
(i) The contracting officer may assign values within the technology
incentive range when contracting performance includes the introduction
of new, significant technological innovation. Use the technology
incentive range only for the most innovative contract efforts.
Innovation may be in the form of--
(A) Development or application of new technology that fundamentally
changes the characteristics of an existing product or system and that
results in increased technical performance, improved reliability, or
reduced costs; or
(B) New products or systems that contain significant technological
advances over the products or systems they are replacing.
(ii) When selecting a value within the technology incentive range,
the contracting officer should consider the relative value of the
proposed innovation to the acquisition as a whole. When the innovation
represents a minor benefit, the contracting officer should consider
using values less than the norm. For innovative efforts that will have
a major positive impact on the product or program, the contracting
officer may use values above the norm.
(e) Evaluation criteria for management/cost control.
(1) The contracting officer should evaluate--
(i) The contractor's management and internal control systems using
contracting office information and reviews made by field contract
administration offices or other DoD field offices;
(ii) The management involvement expected on the prospective
contract action;
(iii) The degree of cost mix as an indication of the types of
resources applied and value added by the contractor;
(iv) The contractor's support of Federal socioeconomic programs;
(v) The expected reliability of the contractor's cost estimates
(including the contractor's cost estimating system);
(vi) The contractor's cost reduction initiatives (e.g., competition
advocacy programs, technical insertion programs, obsolete parts control
programs, dual sourcing, square parts pricing reform, value
engineering);
(vii) The adequacy of the contractor's management approach to
controlling cost and schedule; and
(viii) Any other factors that affect the contractor's ability to
meet the cost targets (e.g., foreign currency exchange rates and
inflation rates).
(2) Above normal conditions. (i) The contracting officer may assign
a higher than normal value when the management effort is intense.
Indicators of this are--
(A) The contractor's value added is both considerable and
reasonably difficult;
[[Page 32069]]
(B) The effort involves a high degree of integration or
coordination;
(C) The contractor has a substantial record of active participation
in Federal socioeconomic programs;
(D) The contractor provides fully documented and reliable cost
estimates;
(E) The contractor has an aggressive cost reduction program that
has demonstrable benefits;
(F) The contractor uses a high degree of subcontract competition
(e.g., agressive dual sourcing);
(G) The contractor has a proven record of cost tracking and
control; or
(H) The contractor aggressively seeks process improvements to
reduce costs.
(ii) The contracting officer may justify a maximum value when the
effort--
(A) Requires large scale integration of the most complex nature;
(B) Involves major international activities with significant
management coordination (e.g., offsets with foreign vendors); or
(C) Has critically important milestones.
(3) Below normal conditions. (i) The contracting officer may assign
a lower than normal value when the management effort is minimal.
Indicators of this are--
(A) The program is mature and many end item deliveries have been
made;
(B) The contractor adds minimum value to an item;
(C) The efforts are routine and require minimal supervision;
(D) The contractor provides poor quality, untimely proposals;
(E) The contractor fails to provide an adequate analysis of
subcontractor costs;
(F) The contractor does not cooperate in the evaluation and
negotiation of the proposal;
(G) The contractor's cost estimating system is marginal;
(H) The contractor has made minimal effort to initiate cost
reduction programs;
(I) The contractor's cost proposal is inadequate; or
(J) The contractor has a record of cost overruns or another
indication of unreliable cost estimates and lack of cost control.
(ii) The following may justify a value significantly below normal--
(A) Reviews performed by the field contract administration offices
disclose unsatisfactory management and internal control systems (e.g.,
quality assurance, property control, safety, security); or
(B) The effort requires an unusually low degree of management
involvement.
4. Section 215.404-702 is amended by adding paragraph (b)(1)(iii)
to read as follows:
215.404-72 Modified weighted guidelines method for nonprofit
organizations other than FFRDCs.
* * * * *
(b) * * *
(1) * * *
(iii) Do not assign a value from the technology incentive
designated range.
* * * * *
[FR Doc. 00-12416 Filed 5-19-00; 8:45 am]
BILLING CODE 5000-04-M