SUBPART 236.5--CONTRACT CLAUSES
(Revised October 25, 2000)
236.570 Additional provisions and clauses.
(2) 252.236-7001, Contract Drawings and Specifications.
(2) When the head of the contracting activity has approved use of a separate bid item for mobilization and preparatory work, use either-
(B) Large stockpiles of material which are in excess of the type, kind, and quantity which would be normal for a contractor qualified to undertake the work; or
(B) Vary this percentage to reflect the circumstances of the particular contract, but in no event should mobilization exceed 80 percent of the payment item.
(4) 252.236-7006, Cost Limitation, if the solicitation's bid schedule contains one or more items subject to statutory cost limitations, and if a waiver has not been granted (FAR 36.205).
(5) 252.236-7007, Additive or Deductive Items, if the procedures in 236.303-70 are being used.
(6) 252.236-7008, Contract Prices--Bidding Schedule, if the contract will contain only unit prices for some items.
(2) 252.236-7012, Military Construction on Kwajalein Atoll--Evaluation Preference, when contract performance will be on Kwajalein Atoll.