(Revised October 14, 1998)
252.217-7000 Exercise of Option to
Fulfill Foreign Military Sales Commitments.
As prescribed in 217.208-70(a), use
the following clause:
(b) The foreign military sales commitments are for:
|
|
ALTERNATE I (DEC 1991)
As prescribed in 217.208-70(a)(1),
substitute the following paragraph (b) for paragraph (b) of the basic clause:
(2) Accelerate the rate of delivery called for under this contract, at a price or cost established before contract award or to be established by negotiation as provided in this clause.
(2) If there is no Production Surge Plan in the contract, the Contractor shall, within 30 days from the date of award, furnish the Contracting Officer a delivery schedule showing the maximum sustainable rate of delivery for items in this contract. This delivery schedule shall provide acceleration by month up to the maximum sustainable rate of delivery achievable within the Contractor's existing facilities, equipment, and subcontracting structure.
(3) The Contractor shall not revise the option delivery schedule without approval from the Contracting Officer.
(2) The Contracting Officer will provide a preliminary oral or written notice to the Contractor stating the quantities to be added or accelerated under the terms of this clause, followed by a contract modification incorporating the transmitted information and instructions. The notice and modification will establish a not-to-exceed price equal to the highest contract unit price or cost of the added or accelerated items as of the date of the notice.
(3) The Contractor will not be required to deliver at a rate greater than the maximum sustainable delivery rate under paragraph (b)(2) of this clause, nor will the exercise of this option extend delivery more than 24 months beyond the scheduled final delivery.
(2) Failure to agree on a cost or price in negotiations resulting from the exercise of this option shall constitute a dispute concerning a question of fact within the meaning of the Disputes clause of this contract. However, nothing in this clause shall excuse the Contractor from proceeding with the performance of the contract, as modified, while any resulting claim is being settled.
252.217-7002 Offering Property for
Exchange.
As prescribed in 217.7005, use the
following provision:
(b) The property is located at (insert address) . Offerors may inspect the property during the period (insert beginning and ending dates and insert hours during day) .
252.217-7003 Changes.
As prescribed in 217.7104(a), use the
following clause:
(2) Work itemized;
(3) Place of performance of the work;
(4) Time of commencement or completion of the work; and
(5) Any other requirement of the job order.
(2) The Contracting Officer may grant an extension of this period if the Contractor requests it within the ten day period.
(3) If the circumstances justify it, the Contracting Officer may accept and grant a request for equitable adjustment at any later time prior to final payment under the job order, except that the Contractor may not receive profit on a payment under a late request.
(d) Failure to agree to any adjustment shall be a dispute within the meaning of the Disputes clause.
(e) Nothing in this clause shall excuse the Contractor from proceeding with the job order as changed.
252.217-7004 Job Orders and Compensation.
As prescribed in 217.7104(a), use the
following clause:
(b) Whenever the Contracting Officer determines that a vessel, its cargo or stores, would be endangered by delay, or whenever the Contracting Officer determines that military necessity requires that immediate work on a vessel is necessary, the Contracting Officer may issue a written order to perform that work and the Contractor hereby agrees to comply with that order and to perform work on such vessel within its capabilities.
(2) The Contractor shall, upon request, furnish the Contracting Officer with a breakdown of costs incurred by the Contractor and an estimate of costs expected to be incurred in the performance of the work. The Contractor shall maintain, and make available for inspection by the Contracting Officer or the Contracting Officer's representative, records supporting the cost of performing the work.
(3) Failure of the parties to agree upon the price of the work shall constitute a dispute within the meaning of the Disputes clause of the Master Agreement. In the meantime, the Contractor shall diligently proceed to perform the work ordered.
(3) Failure of the parties to agree upon the price shall constitute a dispute under the Disputes clause. In the meantime, the Contractor shall diligently proceed to perform the work ordered.
252.217-7005 Inspection and Manner
of Doing Work.
As prescribed in 217.7104(a), use the
following clause:
(b)(1) Except as provided in paragraph (b)(2) of this clause, and unless otherwise specifically provided in the job order, all operational practices of the Contractor and all workmanship, material, equipment, and articles used in the performance of work under the Master Agreement shall be in accordance with the best commercial marine practices and the rules and requirements of the American Bureau of Shipping, the U.S. Coast Guard, and the Institute of Electrical and Electronic Engineers, in effect at the time of Contractor's submission of bid (or acceptance of the job order, if negotiated).
(2) If the Contractor fails to proceed promptly with the replacement or correction of the material or workmanship, the Government may replace or correct the defective or nonconforming material or workmanship and charge the Contractor the excess costs incurred.
(3) As specified in the job order, the Contractor shall provide and maintain an inspection system acceptable to the Government.
(4) The Contractor shall maintain complete records of all inspection work and shall make them available to the Government during performance of the job order and for 90 days after the completion of all work required.
(e) The Contractor shall-
(2) Maintain a reasonable system of inspection over activities taking place in the vicinity of the vessel's magazines, fuel oil tanks, or storerooms containing flammable materials;
(3) Maintain a reasonable number of hose lines ready for immediate use on the vessel at all times while the vessel is berthed alongside the Contractor's pier or in dry dock or on a marine railway;
(4) Unless otherwise provided in a job order, provide sufficient security patrols to reasonably maintain a fire watch for protection of the vessel when it is in the Contractor's custody;
(5) To the extent necessary, clean, wash, and steam out or otherwise make safe, all tanks under alteration or repair;
(6) Furnish the Contracting Officer or designated representative with a copy of the "gas-free" or "safe-for-hotwork" certificate, provided by a Marine Chemist or Coast Guard authorized person in accordance with Occupational Safety and Health Administration regulations (29 CFR 1915.14) before any hot work is done on a tank;
(7) Treat the contents of any tank as Government property in accordance with the Government Property (Fixed-Price Contracts) clause; and
(8) Dispose of the contents of any tank only at the direction, or with the concurrence, of the Contracting Officer.
(2) Protect the stern tube and propeller hubs from frost damage.
(2) Provide Government personnel attached to the vessel access to the vessel at all times.
(i)(1) The Government does not guarantee the correctness of the dimensions, sizes, and shapes set forth in any job order, sketches, drawings, plans, or specifications prepared or furnished by the Government, unless the job order requires that the Contractor perform the work prior to any opportunity to inspect.
252.217-7006 Title.
As prescribed in 217.7104(a), use the
following clause:
(b) Upon completion of the job order, or with the approval of the Contracting Officer during performance of the job order, all Contractor-furnished materials and equipment not incorporated in, or placed on, any vessel, shall become the property of the Contractor, unless the Government has reimbursed the Contractor for the cost of the materials and equipment.
(c) The vessel, its equipment, movable stores, cargo, or other ship's materials shall not be considered Government-furnished property.
252.217-7007 Payments.
As prescribed in 217.7104(a), use the
following clause:
(b) Upon submission by the Contractor of invoices in the form and number of copies directed by the Contracting Officer, and as approved by the Contracting Officer, the Government will make progress payments as work progresses under the job order.
(2) The Government need not make progress payments for invoices aggregating less than $5,000.
(3) The Contracting Officer shall approve progress payments based on the value, computed on the price of the job order, of labor and materials incorporated in the work, materials suitably stored at the site of the work, and preparatory work completed, less the aggregate of any previous payments.
(4) Upon request, the Contractor will furnish the Contracting Officer any reports concerning expenditures on the work to date that the Contracting Officer may require.
(d) The Contracting Officer may direct that progress payments be based on the price of the job order as adjusted as a result of change orders under the Changes clause of the Master Agreement. If the Contracting Officer does not so direct-
(2) Reductions resulting from decreases shall be made for the purposes of subsequent progress payments as soon as the amounts are determined under the Changes clause of the Master Agreement.
(f) All materials, equipment, or any other property or work in process covered by the progress payments made by the Government, upon the making of those progress payments, shall become the sole property of the Government, and are subject to the provisions of the Title clause of the Master Agreement.
252.217-7008 Bonds.
As prescribed in 217.7104(a), use the
following clause:
(b) If the solicitation does not require a bid bond, the Offeror shall not include in the price any contingency to cover the premium of such a bond.
(c) Even if the solicitation does not require bonds, the Contracting Officer may nevertheless require a performance and payment bond, in form, amount, and with a surety acceptable to the Contracting Officer. Where performance and payment bond is required, the offer price shall be increased upon the award of the job order in an amount not to exceed the premium of a corporate surety bond.
(d) If any surety upon any bond furnished in connection with a job order under this agreement fails to submit requested reports as to its financial condition or otherwise becomes unacceptable to the Government, the Contracting Officer may require the Contractor to furnish whatever additional security the Contracting Officer determines necessary to protect the interests of the Government and of persons supplying labor or materials in the performance of the work contemplated under the Master Agreement.
252.217-7009 Default.
As prescribed in 217.7104(a), use the
following clause:
(2) Make progress, so as to endanger performance of the job order; or
(3) Perform any of the other provisions of this agreement or a job order.
(c) If the Contractor's failure to perform is caused by the default of a subcontractor, and if such default arises out of causes beyond the control of both the Contractor and subcontractor, and without the fault or negligence of either, the Contractor shall not be liable for any excess costs for failure to perform, unless the supplies or services to be furnished by the subcontractor were obtainable from other sources in sufficient time to permit the Contractor to perform the job order within the time specified.
(d) If the Government terminates the job order in whole or in part as provided in paragraph (a) of this clause-
(ii) If the work is to be completed at the plant, the Government may use all tools, machinery, facilities, and equipment of the Contractor determined by the Contracting Office to be necessary for that purpose.
(iii) If the cost to the Government of the work procured or completed (after adjusting such cost to exclude the effect of changes in the plans and specifications made subsequent to the date of termination) exceeds the price fixed for work under the job order (after adjusting such price on account of changes in the plans and specifications made before the date of termination), the Contractor, or the Contractor's surety, if any, shall be liable for such excess.
(ii) The Government shall pay to the Contractor the job order price for completed items of work delivered to and accepted by the Government, and the amount agreed upon by the Contractor and the Contracting Officer for manufacturing materials delivered to and accepted by the Government, and for the protection and preservation of property. Failure to agree shall be a dispute concerning a question of fact within the meaning of the Disputes clause.
(f) If the Contractor fails to complete the performance of a job order within the time specified, or any extension, the actual damage to the Government for the delay will be difficult or impossible to determine.
(2) If the Government terminates the job order, the Contractor shall be liable, in addition to the excess costs provided in paragraph (d) of this clause, for liquidated damages accruing until such time as the Government may reasonably obtain completion of the work.
(3) The Contractor shall not be charged with liquidated damages when the delay arises out of causes beyond the control and without the fault or negligence of the Contractor. Subject to the provisions of the Disputes clause of the Master Agreement, the Contracting Officer shall ascertain the facts and the extent of the delay and shall extend the time for performance when in the judgment of the Contracting Officer, the findings of fact justify an extension.
252.217-7010 Performance.
As prescribed in 217.7104(a), use the
following clause:
(b) The Government shall deliver the vessel described in the job order at the time and location specified in the job order. Upon completion of the work, the Government shall accept delivery of the vessel at the time and location specified in the job order.
(c) The Contractor shall, without charge and without specific requirement in a job order-
(2) Supply and maintain suitable brows and gangways from the pier, dry dock, or marine railway to the vessel;
(3) Treat salvage, scrap or other ship's material of the Government resulting from performance of the work as items of Government-furnished property, in accordance with the Government Property (Fixed Price Contracts) clause;
(4) Perform, or pay the cost of, any repair, reconditioning or replacement made necessary as the result of the use by the Contractor of any of the vessel's machinery, equipment or fittings, including, but not limited to, winches, pumps, rigging, or pipe lines; and
(5) Furnish suitable offices, office equipment and telephones at or near the site of the work for the Government's use.
(2) The Contractor shall not conduct dock and sea trials not specified in the job order without advance approval of the Contracting Officer. Dock and sea trials not specified in the job order shall be at the Contractor's expense and risk.
(3) The Contractor shall provide and install all fittings and appliances necessary for dock and sea trials. The Contractor shall be responsible for care, installation, and removal of instruments and apparatus furnished by the Government for use in the trials.
252.217-7011 Access to Vessel.
As prescribed at 217.7104(a), use the
following clause:
(2) Representatives of offerors on other contemplated Government work.
252.217-7012 Liability and Insurance.
As prescribed in 217.7104(a), use the
following clause:
(b) Loss or damage to the vessel, materials, or equipment.
(2) The Government does not assume any risk with respect to loss or damage compensated for by insurance or otherwise or resulting from risks with respect to which the Contractor has failed to maintain insurance, if available, as required or approved by the Contracting Officer.
(3) The Government does not assume risk of and will not pay for any costs of the following:
(B) Defective materials or equipment furnished by the Contractor or its subcontracts; or
(C) Workmanship, materials, or equipment which do not conform to the requirements of the contract, whether or not the defect is latent or whether or not the nonconformance is the result of negligence.
(B) All or substantially all of the Contractor's operation at any one plant.
(5) No party other than the Contractor shall have any right to proceed directly against the Government or join the Government as a co-defendant in any action.
(6) Notwithstanding the foregoing, the Contractor shall bear the first $5,000 of loss or damage from each occurrence or incident, the risk of which the Government would have assumed under the provisions of this paragraph (b).
(2) The indemnity includes, without limitation, suits, actions, claims, costs, or demands of any kind, resulting from death, personal injury, or property damage occurring during the period of performance of work on the vessel or within 90 days after redelivery of the vessel. For any claim, etc., made after 90 days, the rights of the parties shall be as determined by other provisions of this agreement and by law. The indemnity does apply to death occurring after 90 days where the injury was received during the period covered by the indemnity.
(ii) Workers Compensation Insurance (or its equivalent) covering the employees engaged on the work.
(3) Upon request of the Contracting Officer, the Contractor shall provide evidence of the insurance required by paragraph (d) of this clause.
(f) The Contractor shall give the Contracting Officer written notice as soon as practicable after the occurrence of a loss or damage for which the Government has assumed the risk.
(2) If a claim or suit is later filed against the Contractor as a result of the event, the Contractor shall immediately deliver to the Government every demand, notice, summons, or other process received by the Contractor or its employees or representatives.
(3) The Contractor shall cooperate with the Government and, upon request, shall assist in effecting settlements, securing and giving evidence, obtaining the attendance of witnesses, and in the conduct of suits. The Government shall reimburse the Contractor for expenses incurred in this effort, other than the cost of maintaining the Contractor's usual organization.
(4) The Contractor shall not, except at its own expense, voluntarily make any payment, assume any obligation, or incur any expense other than what would be imperative for the protection of the vessel(s) at the time of the event.
(ii) If the Government determines that the risk of the loss or damage is within the scope of the risks assumed by the Government under this clause, the Government will reimburse the Contractor for the reasonable, allowable cost of the replacement or repair, plus a reasonable profit (if the work or replacement or repair was performed by the Contractor) less the deductible amount specified in paragraph (b) of this clause.
(iii) Payments by the Government to the Contractor under this clause are outside the scope of and shall not affect the pricing structure of the contract, and are additional to the compensation otherwise payable to the Contractor under this contract; or
(ii) Terminate the repair of any part or all of the vessel(s) under the Termination for Convenience of the Government clause of this agreement.
252.217-7013 Guarantees.
As prescribed in 217.7104(a), use the
following clause:
(b) If the Contractor or any subcontractor has a guarantee for work performed or materials furnished that exceeds the 90 day period, the Government shall be entitled to rely upon the longer guarantee until its expiration.
(c) With respect to any individual work item identified as incomplete at the time of redelivery of the vessel(s), the guarantee period shall run from the date the item is completed.
(d) If practicable, the Government shall give the Contractor an opportunity to correct the deficiency.
(2) If correction and repairs are performed by other than the Contractor, the Contracting Officer may discharge the Contractor's liability by making an equitable deduction in the price of the job order.
(f) At the option of the Contracting Officer, defects and deficiencies may be left uncorrected. In that event, the Contractor and Contracting Officer shall negotiate an equitable reduction in the job price. Failure to agree upon an equitable reduction shall constitute a dispute under the Disputes clause of this agreement.
252.217-7014 Discharge of Liens.
As prescribed in 217.7104(a), use the
following clause:
(b) If any lien or right in rem is not immediately discharged, the Government, at the expense of the Contractor, may discharge, or cause to be discharged, the lien or right.
252.217-7015 Safety and Health.
As prescribed in 217.7104(a), use the
following clause:
Nothing contained in the Master Agreement or any job order shall relieve the Contractor of any obligations it may have to comply with-
(b) The Safety and Health Regulations for Ship Repairing (29 CFR 1915); or
(c) Any other applicable Federal, State, and local laws, codes, ordinances, and regulations.
252.217-7016 Plant Protection.
As prescribed in 217.7104(a), use the
following clause:
(b) The Contractor shall also provide whatever additional safeguards are necessary to protect the plant and work in process from espionage, sabotage, and enemy action.
(2) The costs reimbursed shall not include any overhead allowance, unless the overhead is incident to the construction or installation of necessary security devices or equipment.
(2) No such device or equipment shall become a fixture as a result of its being affixed to realty not owned by the Government.
252.217-7017 Time of Delivery.
As prescribed in 217.7203(a)(1), use
the following clause:
(b) The Contractor shall complete deliveries within the hours prescribed in the schedule of this contract and on the days specified by the order.
(c) Orders requiring delivery within 24 hours from Contractor receipt are governed by paragraph (e) of the Requirements clause of this contract.
ALTERNATE I (DEC 1991)
As prescribed in 217.7203(a)(1), substitute
the following paragraph (c) for paragraph (c) of the basic clause:
(b) The Offeror shall not change any place of performance between the date set for receipt of offers and the award, except where time permits and then only after receipt of the Contracting Officer's written approval.
(c) The Contractor shall not change any place of performance after contract award without advance approval by the Contracting Officer.
252.217-7019 Sanitary Conditions.
As prescribed in 217.7203(a)(3), use
the following clause:
(b) The Government reserves the right to inspect and test at any reasonable times all plant facilities, machinery, equipment, and parts used in the production, processing, handling, storage, transportation, or delivery of supplies under this contract.
(c) The Contracting Officer or representative shall notify the Contractor in writing of any failure to meet the sanitary standards (including bacteriological requirements) prescribed by this contract. If the Contractor does not correct the failure within three days from receipt of notice, the Contracting Officer may-
(2) Suspend work (wholly or partially) under the contract for ten days or any longer period considered necessary to allow correction of the failure.
(e) During the suspension period, the Government reserves the right to acquire similar supplies from other sources, on whatever terms and in whatever manner the Contracting Officer considers appropriate. The Contractor shall be liable to the Government for any excess costs for those similar supplies.
(f) If the Contractor does not correct the failure within the suspension period, the Contracting Officer may terminate for default the unexpired portion of this contract without allowing additional time for correction, notwithstanding paragraph (a)(2) of the Default (Fixed-Price Supply and Service) clause of this contract.
ALTERNATE I (DEC 1991)
As prescribed in 217.7203(a)(3), add
the following to paragraph (d) of the basic clause:
In a suspension, the quantity of supplies designated in the schedule as a minimum shall be reduced by an amount proportionate to the ratio between (1) the number of days the work is suspended; and (2) the number of days in the contract period. The quantity of supplies designated as maximum shall not be reduced.
252.217-7020 Examination and Testing.
As prescribed in 217.7203(b)(1), use
the following clause:
(b) Samples.
(2) Samples selected at origin shall be furnished at the Contractor's expense, and shall be considered representative of all the products delivered to the Government from the lot sampled.
(3) Samples selected at destination shall be furnished at Government expense, and shall be considered representative of all of that type product delivered to the Government on the date sampled.
(4) When samples are selected from containers of 1/2 gallon size or smaller, the entire contents of the container shall constitute the sample. When samples are selected from containers larger than 1/2 gallon, a 1/2 pint sample shall be taken for laboratory analysis.
(d) Deficiencies in products.
(2) The Contracting Officer may suspend work under this contract for up to ten days when three out of the last five consecutive lots tested are nonconforming for the same specification requirement, or when any deficiency causes the production of a product which is considered to be a health hazard.
(2) The Contractor shall use the suspension period to correct the deficiencies. The Contractor shall notify the Government when corrective action is complete.
(3) The Contracting Officer shall lift the suspension only after the Government has verified the corrective action and notified the Contractor in writing.
(4) The suspension does not extend the life of this contract and shall not be considered sufficient reason for extending the delivery time.
(5) If the Contractor does not correct the failure within the suspension period, the Contracting Officer may terminate for default the unexpired portion of this contract without allowing additional time for correction, notwithstanding paragraph (a)(2) of the Default (Fixed-Price Supply and Service) clause of this contract.
ALTERNATE I (DEC 1991)
As prescribed in 217.7203(b)(1), add
the following to paragraph (d)(2) of the basic clause:
In a suspension, the quantity of supplies designated in the schedule as minimum shall be reduced by an amount proportionate to the ratio between (i) the number of days the work is suspended; and (ii) the number of days in the contract period. The quantity of supplies designated as maximum shall not be reduced.
252.217-7021 Deficiency Adjustment.
As prescribed in 217.7203(b)(2), use
the following clause:
(2) Milk solids nonfat. Subtract the total pounds of milk solids non-fat delivered from the total pounds of milk solids non-fat required to be delivered, and multiply the remainder by the milk solids non-fat value. The milk solids non-fat value is 1.45 multiplied by the average Central States top price for "Extra Grade, Non-fat Dry Milk, Spray (bags)" during the monthly period for which the deficiency is computed, as reported in the Dairy Market News.
(3) Total solids. Add to the total solids delivered the total amount of any shortages for butterfat and milk solids non-fat that the Contractor has already reimbursed. Subtract this amount from the total solids required to be delivered. Multiply the remainder by the milk solids non-fat value.
(c) The butterfat, milk solids non-fat, and total solids content of one type of product shall not be averaged with or offset against the content of another type of product, and the content of products delivered in any one monthly period will not be averaged with or offset against the content of products delivered in any other monthly period.
(d) The Contractor shall identify the tare weights of all containers on the shipping documents, and furnish a copy to the Government inspector at destination. The tare weight of dispenser containers shall include all parts of the container delivered as a unit, including lids, tubes, and seals. If different types of containers with different tares are included in a single delivery, the Contractor shall furnish the tare weight and identifying characteristics of each type of container.
(e) The Government shall inspect a representative sample of the line item. If volume and net weight shortages are found, the Government will adjust the entire quantity of the line item delivered on the day the shortage is discovered. For the purpose of determining net weight, the following weight factors apply:
|
|
Chocolate flavored milk or drink |
|
Milk whole fresh, buttermilk fluid, milk whole fresh cultured, and milk skim fresh |
|
Fresh cream (18 percent butterfat or less), half-and-half fresh, and cream sour cultured |
|
Fresh cream (more than 18 percent butterfat) |
|
Cottage cheese,
butter, and other
non-frozen products |
|
Ice cream and frozen desserts | Applicable commodity specification |
252.217-7022 Code Dating.
As prescribed in 217.7203(a)(4), use
the following clause:
(b) Before using a code, the Contractor shall-
(2) Obtain the Contracting Officer's approval in writing.
252.217-7023 Marking.
As prescribed in 217.7203(a)(5), use
the following clause:
Commercial markings are acceptable, notwithstanding any specification references to MIL-STD-129.
252.217-7024 Responsibility for Containers
and Equipment.
As prescribed in 217.7203(a)(6), use
the following clause:
(2) Remove all empty, reusable containers from Government premises at the time of each delivery, unless the Contracting Officer grants permission in writing for less frequent removal.
252.217-7025 Containers and Equipment.
As prescribed in 217.7203(b)(3), use
the following clause:
(b) The Contractor shall install, service, and maintain any Contractor-furnished bulk milk dispenser cabinets to the Contracting Officer's satisfaction. The Contractor has sole responsibility for the supply, installation, maintenance, and removal of the cabinets, including labor and material costs, and for any damage to, or loss or destruction of, such cabinets.
(c) When the Contractor fails to furnish milk dispenser cabinets or milk dispenser containers as required in the schedule, or does not properly service, maintain, and repair such dispenser cabinets, so that milk cannot be dispensed as needed by the Government, the Contractor shall, for as long as such conditions exist, deliver a sufficient quantity of milk in half-pint containers to satisfy orders for milk dispenser containers. The price per gallon for milk dispenser containers shall apply.
(d) When any loss of contents of a dispenser container occurs (including loss due to contamination, spoilage, or leakage) as a result of functional failure of the dispenser cabinet or dispenser containers, the Contractor shall immediately replace the lost contents without cost to the Government, unless such functional failure was due to a general power failure at the Government installation.
252.217-7026 Identification of Sources
of Supply.
As prescribed in 217.7303, use the
following provision:
(b) The apparently successful Offeror agrees to complete and submit the following table before award:
|
||||||
|
|
|
|
|||
|
|
|
Company |
|
Part No. |
|
|
|
|
||||
|
|
|
|
|
|
|
______ |
|
|
_________ |
|
________ | _______ |
(1) List each deliverable item of supply and item of technical data. | ||||||
(2) If there is no national stock number, list "none." | ||||||
(3) Use "Y" if the item is a commercial item; otherwise use "N." If "Y" is listed, the Offeror need not complete the remaining columns in the table. | ||||||
(4) For items of supply, list all sources. For technical data, list the source. | ||||||
(5) For items of supply, list each source's part number for the item. | ||||||
(6) Use "Y" if the source of supply is the actual manufacturer; "N" if it is not; and "U" if unknown. |
252.217-7027 Contract Definitization.
As prescribed in 217.7406(b), use the
following clause:
(b) The schedule for definitizing this contract action is as follows (insert target date for definitization of the contract action and dates for submission of proposal, beginning of negotiations, and, if appropriate, submission of the make-or-buy and subcontracting plans and cost or pricing data):
(ii) All clauses required by law as of the date of the Contracting Officer's determination; and
(iii) Any other clauses, terms, and conditions mutually agreed upon.
252.217-7028 Over and Above Work.
As prescribed in 217.7702, use a clause
substantially as follows:
(ii) Not covered by the line item(s) for the basic work under the contract; and
(iii) Necessary in order to satisfactorily complete the contract.
(2) Government review, verification, and authorization of the work; and
(3) Proposal pricing, submission, negotiation, and definitization.
(d) The Government shall-
(2) Verify that the proposed work is required and not covered under the basic contract line item(s);
(3) Verify that the proposed corrective action is appropriate; and
(4) Authorize over and above work as necessary.
(f) Failure to agree on the price of over and above work shall be a dispute within the meaning of the Disputes clause of this contract.