Previous Page Next Page PGI 211.5 DFARS Home Page

SUBPART 211.5---LIQUIDATED DAMAGES

(Revised October 1, 2020)

 

 



 211.500 Scope.
 211.503 Contract clauses.


211.500  Scope.

This subpart and FAR subpart 11.5 do not apply to liquidated damages for comprehensive subcontracting plans under the Test Program for Negotiation of Comprehensive Small Business Subcontracting Plans. See 219.702-70 for coverage of liquidated damages for comprehensive subcontracting plans.

 

211.503  Contract clauses.

 

      (b)  Use the clause at FAR 52.211-12, Liquidated Damages--Construction, in all construction contracts exceeding $750,000, except cost-plus-fixed-fee contracts or contracts where the contractor cannot control the pace of the work.  Use of the clause in contracts of $750,000 or less is optional.

 

 

 


Previous Page Next Page PGI 211.5 DFARS Home Page